Status Update - 2/28/19
February 28, 2019
| Status Item | Current Status | Previous Status | Comment |
| Schedule | yellow | yellow | |
| Resources | green | green | |
| Financials | yellow | yellow | Small variance of actual vs budgeted hours requirement review activities & build |
| Quality | green | green | |
| Project Issues | green | green |
| Key Deliverables | % | Comments | Timeline |
| Requirement Sign-off | 98% | In Progress | 12/14 |
| Data Model/Mapping | 100% | All objects built. Minor changes to data model pending. | 1/12 |
| Build | 78% | Sprint 3 (2b): 2/18-3/1 | 3/28 |
| Integration | 13% | Accounts and Terms loaded to UAT | 3/28 |
| Training/UAT | 0% | Not Started | 4/1 |
For the detailed February 28, 2019 status report, click here.